Abstract

The feasibility study is one of the principal documents in building a hydropower plant consisting of technical, economic, and financial aspects. Contained technical studies on civil, mechanical, and electrical. This requires data on hydrologic, geology, land contours, river discharge, water catchment areas, and so on. Economic and financial studies include cost and financial parameters such as; BEP, IRR, NVP, BCR, and others. The installed capacity of a hydropower plant is given in optimization based on the Flow Duration Curve (FDC) and the Capacity Factor (CF) used the Newton Interpolation Method. The results showed that the installed power capacity was 11.99 MW. The water discharge was 31.603 m3/secs and the effective head was 37.5 meters. Annual income is around IDR 103.026 billion. Finally, HPP Lubuak Gadang is technically, economically, and financially feasible, so it is feasible to carry out the next process.

References

[1] K. Kim, T. Park, S. Bang, and H. Kim, “Real options-based framework for hydropower plant adaptation to climate change,” J. Manag. Eng., vol. 33, no. 3, p. 4016049, 2017.

[2] P. 19 ESDM, “Electric Price HPP per KWH,” 2015.

[3] P. 3 ESDM, “Electric Price HPP per KWH,” 2015.

[4] Dempo, “Feasibility Study of TA Lubuak Gadang,” Padang, 2015.

[5] M. C. Tuna, “Feasibility Assessment of Hydroelectric Power Plant in Ungauged River Basin : A Case Study,” Arab J Sci Eng, vol. 38, no. June, pp. 1359–1367, 2015.

[6] Z. Bitar, I. Khamis, Z. Alsaka, and S. Al Jabi, “Pre-feasibility Study for Construction of Mini Hydro Power Plant,” Energy Procedia, vol. 74, pp. 404–413, 2015.

[7] T. Luis E, “Feasibility Study of Hydro PV Hybrid System Operating at a Dam for Water Supply in Soutern Brazil,” J. Power Energy Eng., vol. 3, no. 9, 2015.

[8] Hidayat, Theory an Design Micro Hydro Power Plant. Padang: Bung Hatta Press, 2017.

[9] M. Z. Hidayat, Cahayati, Arnita, “Determination of Optimal Power Capacity for Run of River Hydro Power Plant based on Flow Duration Curve using Newton’s Interpolation Method,” in International Conference on High Voltage Engineering an Power System (ICHVEPS), pp. 1–6, 2017.

[10] S. J. Hidayat, Cahayati, Arnita, “Grid Study of Mini Hydro Power Plant (MHPP) of Palangai Hulu South Pesisir,” in MATEC Web of Conferences, pp. 248–253, 2018.

[11] I. I. Hidayat, Arnita, “Evaluation of Micro Hydro Power Plant (MHPP) using Overall Equipment Effectiveness (OEE) Method,” J. Eng. Appl. Sci., vol. 12, no. 18, pp. 5271–5275, 2017.

[12] J. Hell, “Application of Power Electronics on Hydropower Generation,” J. Phys., 2017.

[13] C. P. J. P. A .Michaela, “Design of 15 kW Micro Hydro Power Plant for Rural Electrification at Valara,” Energy Procedia, vol. 117, pp. 163–171, 2017.

Published
2021-02-28
How to Cite
[1]
Hidayat, A. Azhari Zakri, and I. Satria, “Feasibility Study of Hydro Power Plant (HPP) Lubuak Gadang Sangir South Solok”, IJEEPSE, vol. 4, no. 1, pp. 121-126, Feb. 2021.